Manor Road in Kempston Hardwick to close between 27 July and 5 October 2026

Traffic management plans suggest a 24‑hour closure of the section between Kempston Hardwick station and Eastwood Cottages to allow a plant crossing moving soil for the Universal United Kingdom Resort; pedestrian and local access will be retained at either end.

1 / 3
Image: Project Universal

If you regularly use Manor Road at Kempston Hardwick, here’s what the traffic management plans published by Bedford Borough Council appear to show.

From the plans, it appears that Manor Road will remain open from the Wootton side as far as Kempston Hardwick railway station for pedestrians. From the opposite direction, the road will remain open for residents and businesses near the concrete slab and Eastwood Cottages.

However, there will be no through route. The section of Manor Road between Kempston Hardwick railway station and Eastwood Cottages will be closed.

According to Bedford Borough Council, the closure is required to allow a dedicated plant crossing over Manor Road, enabling the movement of soil between the Lake Zone and Core Zone as construction of the Universal United Kingdom Resort continues. The closure is expected to be in place 24 hours a day from 27 July until 5 October 2026.

If you’re travelling by train, pedestrian access to Kempston Hardwick railway station will only be available from the western side during the works.

As always, this is based on the official traffic management plans, so if you spot anything different once the closure is in place, let everyone know in the comments to help keep everyone updated.

Will this closure affect your daily journey, or have you already got an alternative route planned?